- Boyd County Middle School Gymnasium -
Complete Lighting Renovation of this 5,300 seat
gymnasium. Original plan was a month long
shutdown of the gymnasium. The Scope of
the job was remove 86 1000W High Bay fixtures
and replace them with 76 High Bay Compact
Flourescent Fixtures complete with all new
conductors and breakers. However the
approval of the new fixtures was delayed by bad
wather. This also delayed the delivery of
the fixtures. Instead of 4 weeks to
complete this job Maher Electric had 11 working
days to complete the job before graduation as
promised. We completed this job as
promised. Here are some pictures.
pic1
-
pic2
-
pic3
- Bell County High School - This
project is just getting underway. Complete
renovation of the lighting, bleachers, motorized
goals, curtains in the gymnasium. Complete
renovation of the Auditorium to include a new
Lutron Dimming system for the lighting, new
light fixtures, sound system & fire alarm.
|
|
|